A fatal train crash in the southern state of Oaxaca has caused the fatalities of at least 13 people, an incident likely to revive opposition criticisms regarding the speed and execution of the country's key infrastructure initiatives.
The crash occurred on the Interoceanic Train, a route built to link the Atlantic and Pacific Ocean across the thinnest stretch of the Isthmus of Tehuantepec. This project was designed to provide an alternative rail cargo route to the Panama Canal, intended to promote commercial progress in the area.
“We shall rigorously clarify the cause of this incident,” affirmed the country's president.
The president announced that, of the some 250 individuals on board, another 98 were hurt, with five of those in serious condition. The official stated plans to visit Oaxaca to speak with those involved.
Flagship Project of Previous Administration
The Interoceanic Train was a central development scheme of the former leader, whose time in office finished the year before. This project was intimately linked to his government's economic agenda for the southeastern region.
Another ambitious rail project from that time, a tourist and cargo loop around the Yucatán Peninsula, was also integral to the comprehensive effort to revitalize the economic fortunes of a historically poorer part of the country.
Building Management and Worries
The building of both train projects was managed by the army, marking a dramatic growth of its duties in civilian works. They were built at an rapid speed, surpassing forecasts to be at least partly opened before the end of that administration.
However, this fast-paced schedule had simultaneously sparked significant questions over construction quality.
- Sunday's accident was the third event on the Interoceanic Train in the current year.
- This involves an earlier collision this month when a train struck a truck at a railroad crossing.
- The other major rail project has also seen a couple of non-fatal derailments.
Appeals for Audit and Pause
In the aftermath of the catastrophe, the head of a key rival party urged an prompt halt in the construction and operation of all similar projects.
This stoppage was proposed pending a full technical review. The party emphasized that the situation "requires prompt explanations."
In reply, the national leader asserted that the train had been operating in complete accordance with all safety requirements. Assurances were given that the government would continue to be "diligent" in both the construction and management of these national undertakings.